GEUMHWA PSC

As a leading company in the field of power plant construction, Geumhwa PSC has successfully carried out a number of construction works such as the facilities of power plants, petrochemical, iron & steelmaking plants and LNG plants since 1982.
Based on our rich records and experiences, we constantly develop new construction methods and train engineers.

PROJECT LOCATION CONTRACTOR SCOPE OF WORK CONTRACT PERIOD
Pocheon Combined Cycle Power Plant #1 / GT,ST,BOP,Tank Erection Po-cheon Daewoo E&C GTG(320MW x 2Unit) & STG(312MW x 1Unit), Tank 2015 ~ 2017
Yulchon II Combined Cycle Power Plant / Tubrbine Ereciton Yul-chon Hyundai E&C GTG(317MW x 2Unit) & STG(312MW x 1Unit) 2012 ~ 2014
Shihwaho Tidal Power Plant An-san Daewoo E&C Hydro Turbine(25.4MW X 10unit),  Aux. equipment 2006 ~ 2011
Yicheon Combined Heat Power Plant Yi-cheon Doosan E&C GTG(100MW x 2Unit) and BOP 2002 ~ 2002
Ilsan Combined Cycle Power Plant Il-san GS E&C GTG(100MW x 2Unit) and BOP 1994 ~ 1995
Namjeju Diesel Engine Generator Power Plant Je-ju Hankook Industries Diesel Generator(10MW x 2unit) 1991 ~ 1992
Kumi Combined Heat Power Plant Ku-mi Kumi Industries BLR 225T/H x 2Unit, Aux Coal BLR 200T/H x 1Unit, Aux Oil BLR 80T/H x 1Unit, T/G 85.5MW x 1Unit, PIPE LINE 99KM 1989 ~ 1992
Lucky Yeocheon Combined Heat Power Plant Yeo-cheon Daewoo E&C FBC BLR 210T/H x 1Unit, OIL BLR 100T/H x 1Unit, T/G 55MW x 1Unit 1988 ~ 1989
Banwol Combined Heat Power Plant Ban-wol Banwol Industries BLR 200T/H x 2, T/G 86MW x 1, AUX BLR x 2 1987 ~ 1988
Mok-dong Combined Heat Power Plant Seoul Daewoo E&C 20 MW T/G X 1Unit, Heat Accumulator, Piping 2KM 1985 ~ 1987