Geumhwa PSC leads the future based on abundant construction experience and technology
As a leading company in the field of power plant construction, Geumhwa PSC has successfully carried out a number of construction works such as the facilities of power plants, petrochemical, iron & steelmaking plants and LNG plants since 1982.
Based on our rich records and experiences, we constantly develop new construction methods and train engineers.
PROJECT | LOCATION | CONTRACTOR | SCOPE OF WORK | CONTRACT PERIOD |
---|---|---|---|---|
Hanbit Nuclear Power Plant #5,6 / SGR Replacement Works | Young-gwang | DL E&C | Steam Generator x 4Unit Replacement | 2018 ~ 2021 |
ShinWolsung Nuclear Power Plant #2 | Wol-sung | Samsung C&T | 1,000MW x 1Unit(Mech, Condenser, STG, HVAC, NSSS) | 2009 ~ 2012 |
ShinWolsung Nuclear Power Plant #1 | Wol-sung | Daewoo E&C | 1,000MW x 1Unit(Mech, HVAC, NSSS) | 2008 ~ 2012 |
Uljin Nuclear Power Plant #5, 6 | Ul-jin | Doosan Heavy Industries | 1,000MW x 2Unit(Mech, NSSS) | 2000 ~ 2005 |
Wolsung Nuclear Power Plant #5, 6 | Wol-sung | Hyundai E&C | 700MW x 2Unit(Mech, HVAC, Fuel Handling Sys., Liner, STG) | 1994 ~ 1999 |
Wolsung Nuclear Power Plant #2 | Wol-sung | Hyundai E&C | 700MW x 2Unit(Aux Eq, BOP, Tank) | 1993 ~ 1996 |
Uljin Nuclear Power Plant #1, 2 | Ul-jin | Doosan Heavy Industries | 950MW x 2Unit(Mech, Aux Eq, HVAC, Tank) | 1985 ~ 1989 |
Youngkwang Nuclear Power Plant #1, 2 | Young-kwang | Doosan Heavy Industries | Tank x 25Unit Erection | 1984 ~ 1985 |
Kori Nuclear Power Plant #1, 5, 6 | Ko-ri | Hyundai E&C | Tank x 25Unit Erection | 1982 ~ 1984 |